1 |
Hoisting of decks to required floor level; |
|
2 |
Opening up of bundles, preparing for laying
of decks; |
|
3 |
Cutting of decks to suit its length; |
|
4 |
After cleaning beam surface and markings
completed, decks are laid side by side; |
|
5 |
following installation instructions and
procedures, firing pins or puddle welding is
performed to join decks to beams; |
|
6 |
Edge form is fixed to prevent concrete grout
from falling off; |
|
7 |
weld through composite beam shear studs are
fixed with welding gun; |
|
8 |
Reinforcements are placed over installation
of deckings are completed; |
|
9 |
Clearing the floor ready for concreting. |