3 Pan Klip
System 700 -
Installation
Procedure |
Step 1

The first run of clips
MUST be in position and
fastened, one to each
support, so that they
will correctly engage in
the female and centre
ribs of the first sheet
when the sheet is
located and locked over
the clips. It is
important that the first
sheet be in correct
relation to other
building elements as it
provides the anchor for
other sheets to align
with it.
Step 2

Place the first sheet
longitudinally in
relation to gutter
overhang and position it
over the fastened run of
clips, taking care to
locate the centre rib
first, and engage the
centre and female ribs
onto all clips by foot
pressure.
Step 3

Fix the next run of
clips, one to each
support, with the short
return leg of the clip
over the male rib of the
installed sheet. In the
event that the clip
fouls one the spurs
spaces along the outer
free edge of the male
rib, simply flatten the
spur with a blow from a
rubber hammer mallet to
allow the clip to seat
down over the clip.
Step 4

Position the second
sheet over the second
run of clips, again
locating the centre rib
first. To ensure that
the ends of the sheets
are in line, stretch a
string line across the
bottom of the sheets and
a correct alignment can
be obtained. The
interlocking ribs and
the centre rib must be
fully engaged over each
clip.
This can be easily be
done by walking along
the full length of the
over lapping sheet, i.e.
just walk with one foot
in the tray next to the
over lapping female rib
and the other foot
applying pressure to the
top of the interlocking
ribs at regular
interval. Also apply
foot pressure to the top
of the centre rib over
each clip.

Complete interlocking is
essential, i.e. the
spurs of Duro-Klip along
the underlapping male
ribs must be fully
engaged in the shoulder
of the overlapping
female rib.
As the interlocking ribs
fully engaged, a
distinct “click” will be
heard.
When engaging Duro-Klip
interlocking ribs, stand
only on the sheet being
installed, i.e. the
overlapping sheet, and
not on the preceding
sheet.
Install subsequent
sheets by following
Steps 3 and Steps 4 and
make periodic checks
that the installed
sheets are aligned with
the roof perimeter.
On walling application,
use a rubber mallet to
fully engage the
interlocking ribs and
engage the centre rib
over the clips.
Step 5

If the space left
between the last full
sheet and the fascia or
parapet is more than a
half a sheet, a sheet
can be cut
longitudinally, leaving
the centre rib complete.
This partial sheet can
be fully clipped onto a
row of clips as if for a
full sheet, before
installing the capping
or flashing.
If the space left
between the last full
sheet and the fascia or
parapet is less than a
half sheet width, it can
be covered by capping or
flashing. In this case,
the last sheet should be
secured by cutting clips
in halves and fastening
the male rib at each
purlin with a half clip.

FASTENING METHOD DURO
CLIP

DURO Clip has been
designed for DURO-KLIP
System, it requires two
fasteners per clip and
provides an easy,
positive engagement in
the ribs of the deck.
The two fasteners are
inserted only through
the two punched holes.
Four dimples are also
provided in the clip but
these are for auxiliary
fasteners only, to be
used in the event of a
fastener breaking or a
timber support
splitting.
The clip has a short
return leg and a long
return leg. The clip
must be positioned with
the short leg engaging
over the male rib of the
underlapping sheet.
|